WSDOT Works to Preserve 100 Year Old Bridge

This week by the numbers (project dollars in millions)

Individual highway projects

State

Local

Total

Notes

Total funds

$340

$152

$492

 

Obligated funds*

$222.6 (65%)

$134.8 (89%)

$357.4 (73%)

All funds must be obligated by March 1, 2010

Projects certified

37 (100%)

153 (100%)

190 (100%)

 

Projects obligated

36 (97%)

141 (93%)

177 (93%)

FHWA has obligated some or all funds for the projects

Project delivery to date

Operationally complete

10 (27%)

28 (18%)

38 (20%)

Three state projects were completed this month

Awarded

28 (76%)

132 (86%)

160 (84%)

One local project was awarded
this week

Advertised

31 (84%)

137 (90%)

168 (88%)

No new project advertisements this week

Certified, awaiting advertisment

6 (16%)

16 (10%)

22 (12%)

These projects, including several receiving surplus funds, are planned for upcoming advertisement.

Safety funding buckets ($12 stimulus)

Rumble
Strips

Cable
median
barrier

Total

Notes

Completed

10

0

10

10 projects completed
this week

Awarded

17

6

23

 State stimulus funds only

Advertised 

27

7

34

 State stimulus funds only

Transit projects

Large
urban

Small
urban

Nonurban/
rural

State total

Percent of total $179 awarded

97%

97%

100%

98%

Number of Transit projects obligated

33 of 35

18 of 19

20 of 20

52 of 55
FTA counts all rural projects as one project

August
employment

State

Local

Total

Notes

Payroll

$5

$4.3

$9.3

Average wage is $37/hour

Hours

130,386

121,739

252,125

Up from 144,308 total hours in July

FTEs

754

704

1,458

FTE = 173 hours per month

Employees

2,220

3,213

5,433

Note: Not a count of unique employees

*$4M in state enhancement funds provided to locals. While WSDOT controls $340M, the total for obligation authority is $344M, which is the basis of the percentages in this table, and basis for USDOT review on 3/01/2010.

 

Key issues: State

WSDOT to seek high speed rail funds – WSDOT is applying this week in the second round of applications for a portion of the $8 billion in Recovery Act funds dedicated for High Speed Intercity Passenger Rail (HSIPR). WSDOT is submitting its application for Track 2 funding which closes on October 2. The primary focus of the Track 2 projects is to develop new high speed and intercity passenger rail services, including substantial upgrades to existing services. WSDOT has a total of 25 capital rail projects that qualify for Track 2 consideration. WSDOT applied in August for nearly $435 million in the first round of applications for Track 1 ready-to-go projects. Including both rounds of applications, WSDOT will be applying for a total of nearly $1.3 billion in HSIPR Recovery Act funds.

Five more Recovery Act highway projects completed – WSDOT and local governments across Washington finished five more Recovery Act highway projects, bringing the number of completed projects to 38. The WSDOT project placed eight new low-light traffic cameras on Snoqualmie Pass. Four local governments completed preservation projects.

WSDOT applied for National Fish Passage Program Grant – The WSDOT Stream Restoration Program applied on September 24 for a Recovery Act grant through the U.S. Fish and Wildlife Services’ National Fish Passage Program. WSDOT would direct any award from this grant towards the correction of a fish passage barrier on Anderson Creek on SR 16 in Kitsap County. WSDOT plans to remove two consecutive fish-blocking culverts and replace them with a single 20-foot wide fish passage culvert. The project would open approximately 9,300 meters (5.8 miles) of habitat for chum and coho salmon, as well as steelhead and cutthroat trout.

  • Applications are due on September 30.
  • The award ceiling is $500,000 per project out of $2.8 million available nationwide.

Workers earned over $18 million to date on highway projects – Employees have worked nearly 500,000 hours on state and local Recovery Act highway projects since March, earning over $18.6 million. Employment has increased each month to date as more highway projects advance to construction.

  • Employees worked over 250,000 hours and earned more than $9.3 million on state and local Recovery Act highway projects in August. Workers earned an average hourly wage of $37.
  • WSDOT reports state and local employment data on Recovery Act projects each month. See the measured employment page for more information.

Three more highway projects awarded
Local projects

Key issues: National

Intense nationwide competition for $1.5 billion TIGER Grants – The U.S. Department of Transportation announced it has received 1,400 applications for the discretionary surface transportation grant funds included in the Recovery Act. All 50 states, the District of Columbia, and U.S. territories submitted applications totaling $57 billion, about 38 times the $1.5 billion available.

  • USDOT will utilize a cost-benefit analysis for all applications requesting more than $100 million.
  • WSDOT submitted three applications for high priority projects on September 15. See the TIGER Grant web page for more information.

Reporting begins October 1 for first OMB report – The White House Office of Management and Budget is collecting submissions for its first nationwide stimulus performance report on October 10. Agencies that received stimulus funds have 10 days to submit a thorough report on project spending and job creation. The report will be available to the public later in October on http:// www.recovery.gov.

House T & I Committee Holds Hearing October 1 – The U.S. House Transportation and Infrastructure Committee will hold a hearing October 1 on Recovery Act project performance and employment to date.

  • Washington submitted a status report to the committee on September 17. WSDOT’s latest reports are posted on the stimulus reporting webpage.
  • The next report is expected to be submitted in November.

USDOT announced $20 million for Disadvantaged Business Enterprises (DBE) – The DBE Bonding Assistance program will help DBEs compete for work on Recovery Act transportation projects. The program allows DBEs to apply for reimbursement of bonding premiums and fees incurred when competing for or performing on Recovery Act projects. See the WSDOT Equal Opportunity webpage for more information.

Almost 4,000 Recovery Act highway projects under construction nationwide – The FHWA website reported that 3,966 stimulus projects costing $11 billion are under construction in all 50 states, the District of Columbia, Puerto Rico, and on federal lands. Almost $2 billion has been expended on projects. The FHWA has obligated $19.2 billion of $26.8 billion (72%) to 7,965 projects.

Stimulus project of the week

Stimulus provides long overdue bridge painting project in Wenatchee

Work is underway to repaint the 100 year-old Columbia River Bridge and stimulate the Wenatchee area economy at the same time.
The 1,000-foot long bridge between Wenatchee and East Wenatchee supports a huge irrigation pipe and a pedestrian and bicycle path, which is part of the ten-mile Apple Capital Loop Trail. The City of Wenatchee maintains and operates the bridge and along with local agency partners, recently completed more than a $100,000 in structural repairs to the century-old bridge so it could continue to be used as a critical link in this unique, nationally recognized trail.
Photo of the Columbia River Bridge
The city also determined that the future of the bridge was dependent on significant preservation measures; chief among them, a paint job. The price tag for the first repainting since the bridge was built in 1908 was well beyond the resources of the City and its partners. A solution came in the form of the American Recovery and Reinvestment Act funds. The project received $1,506,749 to clean, paint, illuminate, and add safety and security features.
Gary Owen, Wenatchee City Engineer, said the project is not as easy as it might sound, “The project entails cleaning the entire structure with high pressure water, rust removal with hand tools, priming of bare metal, and painting of the entire structure with two coats of paint. All water and debris must be pumped off the bridge and placed in containers, tested, and disposed of in a sewer treatment plant for the filtered water and a landfill for the paint chips and other debris.”

The bridge must be closed to bikes and pedestrians while the work is underway. The nearby SR 285 Senator George Sellar Bridge, just a few hundred yards downstream had been closed to pedestrian traffic since May due to a construction project adding another eastbound lane. That project removes the sidewalks from the bridge, replacing them with a new structure being added to the south side of the bridge, but that facility won’t be finished until late next year.

The pipeline bridge closes to traffic by October 1 and the Sellar Bridge sidewalk and trail connection will open by then. It is likely, that due to weather, the pipeline bridge painting project will have to shut down for winter and finish next spring. The contractor for the project is F.D. Thomas, Inc. of Central Point, Oregon.

Important dates

September 30: National Fish Passage Program habitat restoration grant applications are due
October 2: Applications for Track 2 FRA High-Speed Passenger Rail grants are due
October 10: WSDOT submits first new federal OMB quarterly performance report
November 20: Next congressional status report due

Websites of interest

WSDOT ARRA website: http://www.wsdot.wa.gov/funding/stimulus
Washington recovery website: http://www.recovery.wa.gov/
Federal recovery website: http://www.recovery.gov/
FHWA recovery website: http://www.fhwa.dot.gov/economicrecovery/index.htm
Federal Transit Administration recovery website: www.fta.dot.gov/recovery
Federal Rail Administration recovery website: www.fra.dot.gov/us/content/2153
Federal Aviation Administration recovery website: http://www.faa.gov/recovery
OMB recovery website: http://www.whitehouse.gov/omb/recovery_default/